Construction of an Alumina Silo 50,000 Ton Capacity (42 mtr Diameter, and 43mtr Height)
Silo Pile cap foundation included 227 numbers of 1.0 meter diameter piles
Silo is constructed on 1.4 meter Thick Pile cap foundation and area of foundation is 1878 Sqm
860 Tons of reinforcement steel fixed and 2470 Cum of concrete poured for the foundation
500mm thick and 42mtr height Silo wall constructed using Slipform method
Slipform sliding completed along with lifting of 400 Ton of load (270 Ton of Fully Assembled Roof and 130 Ton of temporary works, equipments, etc.…)
42 Mtr height Slipform wall construction completed with 830 Ton of reinforcement steel and 3100 Cum concrete in 23 Days of time
Alumina storage Silo wall is post tensioned with 150 tons of Strands and approx. Length of Post Tensioning Ducts is 10,000 meter.
Construction of a Calcined Coke Silo (CPC) 20,000 Ton Capacity (30 mtr Diameter and 62mtr Height)
Silo pile cap foundation included 116 numbers of 1.0 meter diameter piles
Silo is constructed on 1.6 meter Thick Pile cap foundation and area of foundation is 882 Sqm
470 Tons of reinforcement steel fixed and 1540 Cum of concrete poured for the foundation.
Construction of 600mm thick elevated slab 6.00m above from Ground level. 380 Tons of reinforcement steel fixed and 485 Cum of concrete poured for the slab
Construction of 1850mm thick elevated slab 14.00m above from Ground level. 560 Tons of reinforcement steel fixed and 1455 Cum of concrete poured for the 1850mm thick slab
Lower level and elevated level floors constructed prior to start Slipform silo wall for Electrical and Mechanical equipments
500mm thick and 62.0 mtr height Silo wall constructed using Slipform method
Slipform sliding completed along with lifting of 270 Ton of load (170 Ton of Fully Assembled Roof and 100 Ton of temporary works, equipments, etc.…)
8 Mtr height Slipform wall construction completed with 575 Ton of reinforcement steel and 2510 Cum concrete in 21 Days of time
CPC Silo wall is post tensioned with 100 tons of Strands and approx. Length of Post Tensioning Ducts is 7,400 meter.